Project
Gardermoen Pir Nord 2017
Equipment
We delivered equipment for this project in two installments:
2 x 1.5MW mobile heating center and 3 x Heatboy EH36
4.5MW divided into 3 x 1.5MW mobile boilers< /a>.
Assignment
We were tasked with supplying temporary building heat for the drying process, as well as ensuring that the pavements were kept free of ice.